Rover Alcisa finishes the works of the Jenofonte del Metro Avenue in Málaga |
|
Line 1 of the Malaga underground moves forward as planned. Rover Alcisa that participates in the construction of such line has finished the works of the Jenofonte Avenue. This work is planned to be finished in February of this year, which means the start of the first stretch of the underground in Málaga. Rover Alcisa has also finished the complementary works of line 1 that contemplated the building of 4 paddle courts, a surface of 200 metres destined to changing rooms, 3 sport centre tracks of "Cushion 3" one of them with a covered structure, and a volleyball court.
Rover Alcisa participates with Copcisa and Bahía San Kristobal in the construction of the only stretch of the underground that has been out of concession that counts with a surface of 3.000 metres of double way where a structure of 100 metres long is going to be built.

The works will be on time, starting on June 2008 and finishing on February 2010, although the as a whole it will be finish of December. The stretch will count with five stations: Colegios Mayores (High Schools), Rectorado (Chancellery) El Cónsul (the Consul), Hospital Clínico (Clínico Hospital), and Universidad (University).
|